PAGE #2 - PHOTOS FROM AUGUST 25 - DECEMBER 10 2025
Aug 25-Contractors meet adjacent to the site.
Sept 3-Tree removal/site preps
Sept 10-The first truckload of logs being loaded up.
Sept. 12 - The site being leveled.
Sept 14 - Groundbreaking Service!
Sept 15 - Dirt is flying!
Sept 17 - Ground prep continues
Sept 19 - Ready to dig footers
Sept. 22 - Footers being dug
Sept. 23 - Rebar placed in footers
Sept. 24 - Footers being poured.
Sept. 29 - Forming and pouring foundation wall
September 29 - Forms placed and foundation walls and piers poured.
Sept. 30 - Steel arrives
Sept 30 - Foam installed
Oct. 1 - Some posts installed
Oct. 2 - Conduit and backfilled
Oct. 3 - Steel framework installed.
Oct. 6 - Framing begins!
Oct. 8 - Framing is progressing!
Oct. 17 - Trusses arrive!
Shipped in two pieces and assembled on site.
Oct. 20 - Trusses being installed
October 21
Oct. 22 - Last truss going up.
Oct. 22 - First row of sheeting.
Oct. 23 - Roof sheeting continues.
View from Dining Hall
View from back of Lodge
Front of chapel (lobby area)
Looking from the future stage side
Roof is 36 ft. / Ceiling inside is 24 ft.
Oct. 24 - Installing shingles
Oct. 27 - Shingles, plumbing, conduit
Oct. 28 - Conduit, plumbing, stormwater
Oct. 30 - Shale, collar ties, framing
Oct. 31 - Big section of roof completed
Nov. 3 - First porch truss is set
Nov. 4 - Back end wall is closed in.
Nov. 5 - Gable-end windows installed
Nov. 7 - Floor being poured.
Nov. 10 - Stormwater drainage install continues
Nov. 11 - The first snow on the new roof
Nov. 12 - Windows installed
Nov 12 - Stormwater drainage work continues
Nov. 17 - stormwater drainage work continues.
Nov. 18 - Porches and HVAC pad poured
Nov. 20 - Doors Installed
Nov. 21 - Interior framing
November 26 - Interior framing continues
Dec. 2 - Framing above coffee bar. Electrical rough-in has begun.
Looking through the Lobby (fireplace framing)
Sound booth framing
Dec. 5 - Water and sewer lines
Dec. 5 - Rear porch framing
Dec. 8 - HVAC install begins
Dec. 9 - Rear porch roof
Dec. 9 - Rear porch will serve as covered walkway from ADA parking spots
Dec. 5 - Fireplace prep
Dec. 9 - Gas fireplace installed
Dec. 10 - Interior framing
Dec. 10 - Stage-end wiring rough-in